Kendall Bay Remediation

Latest News

  • Remediation works progressing well

    Remediation works, involving the clean up of contaminated sediments in Kendall Bay is progressing well, with the Insitu-stabilisation (ISS) work commencing this week (w/c Feb 24). The ISS works involve the pumping of marine cement into the contaminated sediments below the surface, to form a raft like structure and contain the contaminated sediments permanently.
    Work completed to date has included the establishment of the Staging Site at 140 Tennyson road and installing the majority of the environmental controls, including the installation of the Northern sheet pile walls, the outer and inner silt curtains, the bubble curtains and work continues on southern sheet piles – due to be completed in March 2020.
    The Sheet pile wall in the North was completed within ~4.5 weeks, well in advance of the initial estimated ~8-10 weeks that were scheduled. This allowed a good respite period over the Christmas/New Year period.
    The use of Bubble curtains (whereby a compressor supplies air which blows up bubbles to surface) has been adopted in areas to act as access gates. These bubble curtains control turbidity in the water while allowing for boats/barges to move through the gating areas efficiently, without having to open and close any physical structure.
    Sediment removal in the southern area (to enable the larger equipment/barges to access this shallow area) requires an excavator to remove the sediments and place into purpose built (blue) bins. The bins are then closed to limit the time the sediments are exposed to reduce the potential for odour. The barges transport the bins back to the Staging site whereby they are transported offsite for treatment and disposal.
    Impacts associated with the works include the potential to create odour, intermittent noise and a visual sheen on the surface of the water in the vicinity of the works. Stringent controls and mitigation measures are in place to manage these impacts, as well as Environmental Monitoring for Water Quality, Noise and Air Quality (Odour). No readings have been outside the Project compliance criteria to date.
    Jemena’s Community Liaison Manager, Barbara said that the local community had been patient and supportive of the works. “ Residents have been very understanding and appreciative of these important environmental works that will ultimately leave a lasting legacy”.
    The project is on schedule to be completed in December 2020, weather and site conditions dependant.