March 2021
Works completed to date;
Site Establishment and mobilisiation;
Excavation shoring and asset protection;
Construction of Emissions Control System (ECS);
Construction of Water Treatment Plant (WTP);
Assembly of Stage 1 Odour Control Enclosure (OCE) adjacent to Collegians;
Commence remediation of Area A;
Works to commence from March / April 2021
Relocation of OCE to Stage 2 adjacent to rail line;
Commence remediation of Area B & C;
Site restoration, levelling and grading; and
Site Demobilisation.